Summary:

Project comprises labor, material and services necessary for: Major components of Project Work consist of: Asbestos and lead based paint abatement. Demolition of existing boiler house and construction of a new 4,700 s/f pre-fabricated metal building with three 1,200 HP steam boilers, Selective Catalytic Reactor, 30,000 gallon LPG storage tank, 210,000-gallon fire water storage tank and pump, piping, paving, fencing, retaining wall excavation, manholes, cast in place concrete, asphalt, electrical raceway, wiring, cable, transformers, pole lines, panel boards, switchgear, generator and related work.

Pre-Bid Conference:

Pre-bid Site Inspection: Bids will only be accepted from those Contractors having attended the MANDATORY pre-bid site inspection tour on October 27, 2020, at 10:00 A.M., at which time representatives of the State and prospective bidders shall meet at San Quentin State Prison, West Gate Entrance, San Quentin, Marin County, CA. The State's requirements for Disabled Veteran Business Enterprise (DVBE) participation and other Contract requirements will be presented. For security reasons, attendees should arrive no earlier than one (1) hour before meeting time. Participants must pass screening for COVID-19 (by responses to healthcare questions and temperature reading) and are required to show a valid photo identification (ID) (i.e. Driver License), required at the entrance gate, in order to attend the Walk-through. Further, participants must wear N95 respirator at all times while on prison grounds. N95 respirators will not be provided by the State and are the responsibility of the contractor to provide for themselves.

Successful bidder shall furnish payment and performance bonds, each in the amount of 100 percent of the Contract price.

Security Clearance: Bidders attention is directed to the deadline to contact Ryan Beck, Project Director, at 916-375-4310 no later than 4:00 P.M., October 13, 2020; and provide (1) full name, (2) telephone number, (3) Social Security Number, (4) Identification Number or California Driver's License Number and expiration year, and (5) date of birth; for security clearance to enter Institution. Blue, black, or acid washed denim trousers, camouflage clothing, red or orange jumpsuits, and blue or black chambray shirts, cameras and recording devices will not be allowed. See Document 01 35 53, Correctional Security Project Procedures, for additional requirements.

Contract has been awarded to:

Zovich & Sons, Inc. dba Zovich Construction
Brentwood, CA

To view the awarded contract document and other Event Package documents, go to the Cal eProcure Event Details on the left.


Return to: Real Estate Services Division Solicitations & Contract Awards

CAL EPROCURE

Go to Cal eProcure for the full Event Details & Contact information.

office of state publishing

Go to the Office of State Publishing for Plans and Specs.