QUARTERLY REPORT - 6864

(Revised: 05/1998)

Each department with an active capital outlay appropriation must submit a quarterly report to DOF no later than April 15, July 15, October 15, and January 15 of each calendar year as shown in 6864 Illustration 1.

The fiscal data should include all funding (appropriations and executive orders) related to the project plus any transfers related to each appropriation. Comments should describe the status of the current phase. Detail of change orders should recap any scope changes and construction change orders issued or pending. The schedule, at a minimum, should reflect the original dates (at time of project funding approval), and the latest revised dates and actual dates. In addition, it is helpful to enter into a history of schedule changes.

 

6864 Illustration 1 (Disclaimer: This illustration is currently unavailable. For access, please contact the SAM Unit at SAMUnit@dgs.ca.gov.)

Revisions

No Revisions for this item.